The kitchen contract turns on the cabinet order: a large non-refundable deposit, a long lead time, and a visible idle gap while counters are templated.
This is a checklist of what a kitchen remodel contract has to settle — not a ready-to-sign legal document, and not legal advice. Most states regulate home improvement contracts: required disclosures, cancellation windows, deposit limits and licence display all vary, and some trades carry extra rules. Adapt this, then have a lawyer in your state review it before you put it in front of a customer.
Download as a spreadsheet to work through, or print it to sit alongside your own agreement.
A kitchen contract has to handle money that leaves the contractor's hands before any work happens. The cabinet deposit goes to a supplier and is usually non-refundable once the order is placed, so cancellation terms must exist and be understood at signing. Lead times and the template-to-install gap belong in the schedule, because a customer without a working sink for ten days will assume they have been abandoned unless the contract told them it was coming.
A contract can only be as clear as the scope it references. BidWand drafts the itemised estimate — labour, materials, exclusions and assumptions — that the scope and exclusions clauses point at.
This generates the estimate, not the contract — describe the job and you get the itemised scope to attach. No email needed to see the first one.
A complete estimate you can send to the customer, built from the rate you enter:
| Description | Qty | Unit | Unit price | Total |
|---|---|---|---|---|
| Labor — itemized by task | hrs | hour | your rate | — |
| Materials — with your markup applied | qty | ea / sq ft | cost + markup | — |
| Permits, disposal, access | — | — | — | — |
Plus a plain-English scope summary, assumptions (what had to be guessed), exclusions (what you are not doing — the section that prevents most change-order arguments), and a validity period. Printable, or send the link.
Every figure comes from the rate and markup you supply. We never fill in a market price for you.
sod installation · garage floor epoxy · driveway sealing · pressure washing · interior painting
kitchen remodel · tile installation · bathroom remodel · HVAC · plumbing · electrical · painting · roofing
How to write a contractor estimate · Estimate vs quote vs bid — and which one you should send · What to include in a contractor estimate · How to price a job as a contractor · Should you charge for estimates? · How to follow up on an estimate · How to handle change orders · Estimate vs invoice: what's the difference? · How to raise your prices as a contractor