Not a legal document and not legal advice. Home improvement contracts are regulated differently in every state. Have a lawyer in your state review your agreement before you use it.
| Settled in writing? | |
|---|---|
| ☐ | Parties, licence number, site address and the scope in cubic yards |
| ☐ | The soil condition the price assumes, stated explicitly |
| ☐ | Differing site conditions: unit rates for rock, unsuitable material and groundwater |
| ☐ | Utility locates: who calls, the required wait, and liability for unmarked lines |
| ☐ | Hand-digging obligations within the tolerance zone of marked utilities |
| ☐ | Spoil: hauled or retained, and where retained spoil is placed |
| ☐ | Haul tickets as the basis for load-count billing |
| ☐ | Standby time rate when trucks or inspections delay the crew |
| ☐ | Access route, and responsibility for restoring it |
| ☐ | Erosion control, and who holds the permit that requires it |
Checklist from bidwand.com.